Project overview
Aaradhya Highpark Project Iii Of Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700030611. Aaradhya Highpark Project Iii Of Phase 1 is located at Western Express Highway, Near Singapore International School, Near Singapore International School. This is a New Project being developed by Man Vastucon Llp.
Aaradhya Highpark Project Iii Of Phase 1 has 1 BHK & 2 BHK Apartments with carpet areas ranging from 405 to 605 Sq.ft. Carpet. The Project has total 468 of which 2 are currently available for sale.
Aaradhya Highpark Project Iii Of Phase 1 is being developed on a total land area of 15285 Sq.ft. Aaradhya Highpark Project Iii Of Phase 1 has 2 Wings / Towers Elm,Fir
Project | Developer | Location | Possession |
Aaradhya Highpark - Project 1 Of Phase I | Man Vastucon Llp | Western Express Highway, Near Singapore International School, Near Singapore International School | 30-03-2025 00:00:00 |
Aaradhya Highpark - Project 2 Of Phase I | Man Vastucon Llp | Western Express Highway, Near Singapore International School, Near Singapore International School | 30-03-2025 00:00:00 |
Sector 2A - Wing C | Eversmile Properties Private Limited | Bhaktivedanta Swami Marg, Shrushti Chowk, Mira Road, Shrushti Chowk, Mira Road | 30-06-2027 00:00:00 |
127 Raj Homes A Wing | Raj Homes | Abhilasha Residency Road, Penkar Pada ( Mahajanwadi), Penkar Pada ( Mahajanwadi) | 30-09-2025 00:00:00 |
S3 Skyrise | S3 Smart Spaces Private Limited | Sanghvi S3 Ecocity, Near Hermitage Society, Behind Mahavishnu Temple, Near Dahisar Checkpost, Mira Road (East) Taluka And District Thame, Near Dahisar Checkpost, Mira Road (East) Taluka And District Thame, Sanghvi S3 Ecocity, Near Hermitage Society | 31-12-2027 00:00:00 |
Aaradhya Parkwood 1 | Man Vastucon Llp | Western Express Highway, Near Singapore Internation School, Near Singapore Internation School | 31-12-2028 00:00:00 |
S3 Skygreens | S3 Smart Spaces Private Limited | Sanghvi S3 Ecocity Near Hermitage Society Behind Mahavishnu Temple, Near Dahisar Checkpost Mira Road East Taluka And District Thane, Near Dahisar Checkpost Mira Road East Taluka And District Thane | 30-06-2028 00:00:00 |
Ganesh Darshan | J.V. Realty | Penkarpada Mahajanwadi, Penkarpada Mahajanwadi | 30-07-2026 00:00:00 |
-
Project:
Aaradhya Highpark Project Iii Of Phase 1
-
Location:
-
Western Express Highway, Near Singapore International School, Near Singapore International School
-
Const. Stage:
New Project
-
Possession:
31 Dec 2025
-
Developer:
Man Vastucon Llp
-
Phone:
-
Address:
-
12Th Floor, Krushal Commercial Complex, G M Road, Above Shoppers Stop, Chembur West, 400089
MAHA REARA No: |
P51700030611 |
Project Type |
Residential |
RERA Project Status |
New Project |
Architect |
Disha Design Consultant |
Funding Bank |
INDUSIND BANK LIMITED |
Proposed Possession |
31 Dec 2025 |
Revised Possession |
|
Extended Possession |
|
Litigations |
No Litigations |
Last Modified |
07 Mar 2024 |
Last Retrived |
16 Jan 2025 |
Aaradhya Highpark Project Iii Of Phase 1 QR Code
Aaradhya Highpark Project Iii Of Phase 1
MahaRERA - P51700030611
Type | Area |
1 BHK | 37.62 Sq.mts. ( 405 Sq.ft. ) |
1 BHK | 39.5 Sq.mts. ( 425 Sq.ft. ) |
2 BHK | 56.2 Sq.mts. ( 605 Sq.ft. ) |
1 BHK | 38.92 Sq.mts. ( 419 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Aaradhya Highpark Project Iii Of Phase 1last updated on 16 Jan 2025
as per information obtained from MARA RERA.
Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Completed (No Receiving Station) |
|
|
Na |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Completed |
Landscaping & Tree Planting100% completed
|
|
Completed |
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Completed |
Solid Waste Management And Disposal100% completed
|
|
Completed |
Storm Water Drains100% completed
|
|
Completed |
Street Lighting100% completed
|
|
Completed |
Treatment And Disposal Of Sewage And Sullage Water100% completed
|
|
Completed |
Water Conservation, Rain water Harvesting100% completed
|
|
Completed |
Water Supply100% completed
|
|
Completed |
Buildings / Wings in Aaradhya Highpark Project Iii Of Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Aaradhya Highpark Project Iii Of Phase 1 by Man Vastucon Llplast updated on 16 Jan 2025
as per information obtained from MARA RERA.
Apartments Statistics
468
apartments in total
Saleable Area Statistics (Sq. ft.)
221444
Total
Total 468 apartments in project. 466 apartments booked. 99% apartments booked.
Total 221444 Sq.ft. saleable area. 220634 saleable area booked.
100% area booked.
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
Elm | Dec 2025 | 31 | 1 | 1 | 1 | 2 | 0 | 115 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
1 BHK | 37.62 Sq.mts. ( 405 Sq.ft. ) | 90 | |
1 BHK | 39.5 Sq.mts. ( 425 Sq.ft. ) | 54 | |
2 BHK | 56.2 Sq.mts. ( 605 Sq.ft. ) | 90 | |
234 total apartments / 233 apartments booked. 99% apartments booked. |
Work Description in Building Elm | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
Fir | Dec 2025 | 31 | 1 | 1 | 1 | 2 | 0 | 116 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
1 BHK | 37.62 Sq.mts. ( 405 Sq.ft. ) | 114 | |
1 BHK | 38.92 Sq.mts. ( 419 Sq.ft. ) | 60 | |
2 BHK | 56.2 Sq.mts. ( 605 Sq.ft. ) | 60 | |
234 total apartments / 233 apartments booked. 99% apartments booked. |
Work Description in Building Fir | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Man Vastucon Llp
for Project
Aaradhya Highpark Project Iii Of Phase 1
last updated on
16 Jan 2025
as per information obtained from MARA RERA.
Name |
Company |
Location |
Mobile |
Designation |