Ekta Parksville Phase Iv is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000015239. Ekta Parksville Phase Iv is located at Narangi Bypass Road, Virar, Virar. This is a New Project being developed by Ekta Parksville Homes Pvt. Ltd..

Ekta Parksville Phase Iv has 1 BHK 1, 1 BHK 2, 1 BHK 3, 2 BHK, Shop 1, Shop 2, Shop 3, Shop 4, Shop 5 & Shop 6 Apartments with carpet areas ranging from 119 to 512 Sq.ft. Carpet. The Project has total 318 of which 262 are currently available for sale.

Ekta Parksville Phase Iv is being developed on a total land area of 13812 Sq.ft. Ekta Parksville Phase Iv has 4 Wings / Towers Wing A,Wing B,Wing C,Wing D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Ekta Parksville Phase Iv
  • Location:
  • Narangi Bypass Road, Virar, Virar
  • Const. Stage:
    New Project
  • Possession:
    30 Jun 2022
Developer Details

  • Developer:
    Ekta Parksville Homes Pvt. Ltd.
  • Phone:
  • Address:
  • 401, Hallmark Business Plaza, Sant Dyaneshwar Marg, Opp. Gurunanak Hospital, Kalanagar, Bandra East, 400051
Project RERA Details
MAHA REARA No: P99000015239
Project Type Residential
RERA Project Status New Project
Funding Bank HDFC BANK
Proposed Possession 30 Jun 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 26 Feb 2024
Last Retrived 13 Jan 2025
Ekta Parksville Phase Iv QR Code
Ekta Parksville Phase Iv
MahaRERA - P99000015239
Apartment Details & Configuration
TypeArea
2 BHK 141.78 Sq.mts. ( 450 Sq.ft. )
2 BHK 248.44 Sq.mts. ( 521 Sq.ft. )
2 BHK 350.93 Sq.mts. ( 548 Sq.ft. )
SHOP 1915.74 Sq.mts. ( 169 Sq.ft. )
SHOP 2012.91 Sq.mts. ( 139 Sq.ft. )
SHOP 2115.21 Sq.mts. ( 164 Sq.ft. )
SHOP 2218.99 Sq.mts. ( 204 Sq.ft. )
SHOP 2312.4 Sq.mts. ( 133 Sq.ft. )
SHOP 2416.25 Sq.mts. ( 175 Sq.ft. )
SHOP 2511.43 Sq.mts. ( 123 Sq.ft. )
SHOP 2615.33 Sq.mts. ( 165 Sq.ft. )
1 BHK33.75 Sq.mts. ( 363 Sq.ft. )
2 BHK48.36 Sq.mts. ( 521 Sq.ft. )
3 BHK65.93 Sq.mts. ( 710 Sq.ft. )
Shop 1018.16 Sq.mts. ( 195 Sq.ft. )
Shop 1113.59 Sq.mts. ( 146 Sq.ft. )
Shop 1215.55 Sq.mts. ( 167 Sq.ft. )
Shop 1311.44 Sq.mts. ( 123 Sq.ft. )
Shop 1422.78 Sq.mts. ( 245 Sq.ft. )
Shop 1617.2 Sq.mts. ( 185 Sq.ft. )
Shop 1713.39 Sq.mts. ( 144 Sq.ft. )
Shop 189.86 Sq.mts. ( 106 Sq.ft. )
Shop 712.19 Sq.mts. ( 131 Sq.ft. )
Shop 812.07 Sq.mts. ( 130 Sq.ft. )
Shop 915.58 Sq.mts. ( 168 Sq.ft. )
1 BHK 133.22 Sq.mts. ( 358 Sq.ft. )
1 BHK 231.38 Sq.mts. ( 338 Sq.ft. )
1 BHK 333.89 Sq.mts. ( 365 Sq.ft. )
2 BHK47.52 Sq.mts. ( 512 Sq.ft. )
Shop 112.42 Sq.mts. ( 134 Sq.ft. )
Shop 211.1 Sq.mts. ( 119 Sq.ft. )
Shop 318.36 Sq.mts. ( 198 Sq.ft. )
Shop 412.39 Sq.mts. ( 133 Sq.ft. )
Shop 527.45 Sq.mts. ( 295 Sq.ft. )
Shop 612.33 Sq.mts. ( 133 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Ekta Parksville Phase Ivlast updated on 13 Jan 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Yet To Start
Energy management
Na
Fire Protection And Fire Safety Requirements
Yet To Start
Landscaping & Tree Planting
Yet To Start
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Yet To Start
Solid Waste Management And Disposal
Yet To Start
Storm Water Drains
Yet To Start
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Yet To Start
Water Conservation, Rain water Harvesting
Yet To Start
Water Supply
Yet To Start
Buildings / Wings in Ekta Parksville Phase Iv
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Ekta Parksville Phase Iv by Ekta Parksville Homes Pvt. Ltd.last updated on 13 Jan 2025 as per information obtained from MARA RERA.

13812 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

318 apartments in total
Total
318
Booked
56
Available
262

Saleable Area Statistics (Sq. ft.)

137181 Total
Total
137181
Booked
18312
Available
118869
Total 318 apartments in project. 56 apartments booked. 17% apartments booked.
Total 137181 Sq.ft. saleable area. 18312 saleable area booked.
13% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJun 202216101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK 141.78 Sq.mts. ( 450 Sq.ft. )15
2 BHK 248.44 Sq.mts. ( 521 Sq.ft. )15
None Booked0% Booked
0% Booked
2 BHK 350.93 Sq.mts. ( 548 Sq.ft. )28
SHOP 1915.74 Sq.mts. ( 169 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 2012.91 Sq.mts. ( 139 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 2115.21 Sq.mts. ( 164 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 2218.99 Sq.mts. ( 204 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP 2312.4 Sq.mts. ( 133 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 2416.25 Sq.mts. ( 175 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 2511.43 Sq.mts. ( 123 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 2615.33 Sq.mts. ( 165 Sq.ft. )1
1 Booked100% Booked
100% Booked
66 total apartments / 10 apartments booked. 15% apartments booked.
Work Description in Building Wing ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJun 202216101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.75 Sq.mts. ( 363 Sq.ft. )45
9 Booked20% Booked
20% Booked
2 BHK48.36 Sq.mts. ( 521 Sq.ft. )13
4 Booked30% Booked
30% Booked
3 BHK65.93 Sq.mts. ( 710 Sq.ft. )15
Shop 1018.16 Sq.mts. ( 195 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 1113.59 Sq.mts. ( 146 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 1215.55 Sq.mts. ( 167 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 1311.44 Sq.mts. ( 123 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 1422.78 Sq.mts. ( 245 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 1522.78 Sq.mts. ( 245 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 1617.2 Sq.mts. ( 185 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 1713.39 Sq.mts. ( 144 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 189.86 Sq.mts. ( 106 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 712.19 Sq.mts. ( 131 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 812.07 Sq.mts. ( 130 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 915.58 Sq.mts. ( 168 Sq.ft. )1
1 Booked100% Booked
100% Booked
85 total apartments / 22 apartments booked. 25% apartments booked.
Work Description in Building Wing BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CJun 202216101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK 150.93 Sq.mts. ( 548 Sq.ft. )28
None Booked0% Booked
0% Booked
2 BHK 248.44 Sq.mts. ( 521 Sq.ft. )15
None Booked0% Booked
0% Booked
2 BHK 341.78 Sq.mts. ( 450 Sq.ft. )15
58 total apartments / 2 apartments booked. 3% apartments booked.
Work Description in Building Wing CCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DJun 202216101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK 133.22 Sq.mts. ( 358 Sq.ft. )15
None Booked0% Booked
0% Booked
1 BHK 231.38 Sq.mts. ( 338 Sq.ft. )13
1 BHK 333.89 Sq.mts. ( 365 Sq.ft. )60
16 Booked26% Booked
26% Booked
2 BHK47.52 Sq.mts. ( 512 Sq.ft. )15
Shop 112.42 Sq.mts. ( 134 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 211.1 Sq.mts. ( 119 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 318.36 Sq.mts. ( 198 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 412.39 Sq.mts. ( 133 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 527.45 Sq.mts. ( 295 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 612.33 Sq.mts. ( 133 Sq.ft. )1
None Booked0% Booked
0% Booked
109 total apartments / 22 apartments booked. 20% apartments booked.
Work Description in Building Wing DCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Ekta Parksville Homes Pvt. Ltd.
for Project
Ekta Parksville Phase Iv
last updated on 13 Jan 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation