Project overview

Kakad Paradise Phase 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700006750. Kakad Paradise Phase 2 is located at Part Of 48/4 48/5 48/10 48/11 48/14 48/22 48/23 48/20 48/15 48/18 48/19 48/21 46/3 46/2 45/1. This is a Ongoing being developed by Kakad Housing Corporation.

Kakad Paradise Phase 2 has 1 BHK & 2 BHK Apartments with carpet areas ranging from 458 to 579 Sq.ft. Carpet. The Project has total 200 of which -23 are currently available for sale.

Kakad Paradise Phase 2 is being developed on a total land area of 85112 Sq.ft. out of which 14187 Sq.ft. i.e 17% is reserved for recreational purposes. Kakad Paradise Phase 2 has 2 Wings / Towers Wing C,Wing D

ProjectDeveloperLocationPossession
ArcadiaJangid PropertiesNew Survey Number 60/230-04-2018 00:00:00
12Th AvenueSadguru Baba Developers LlpMira Road31-12-2021 00:00:00
SHUBHAM GARDENSHUBHAM DRASHTI ENTERPRISESNew 1712 30-04-2022 00:00:00
RAJ ENCLAVERATNA PRIYA BUILDERSOld Sno 331 New Sno 27 Hno 5 Of Village Goddev30-12-2022 00:00:00
Keystone ClassicKeystone Classic401107, Thane30-04-2020 00:00:00
BHARGAVR N ENTERPRISESS.N 191 H.N.2B31-12-2019 00:00:00
MANGAL PUSHP HEIGHTSSUNIL MANGILAL JAINOld Sno 668 New Sno 257 Hno 1 /7 Village Bhayander Dist Thane30-12-2023 00:00:00
IDEAL PARKIDEAL BUILDER & DEVELOPERS84 Hissa No 115-08-2019 00:00:00
BALAJI HEIGHTSSHREE BALAJI REALITYOld Sno 2217 New Sno 195730-04-2018 00:00:00
ANAND PARK D WINGR K DEVELOPMENTOld S.N.223 N.S.No.191 H.No.178631-07-2018 00:00:00
SKYLINE-II-MHADAUNIQUE SHANTI NEMINATH DEVELOPERS LLPS No 216P, 221P31-03-2018 00:00:00
SHALOM JOVECOTTADIYIL ENTERPRISESOld Sno 563, 566 New Sno 205,219 Hno 1 And 5 Village Bhayander Dist Thane31-12-2018 00:00:00
Sheetal Complex Wing D EAbhay Builders401107, Thane05-08-2018 00:00:00
Lodha Mira Road Project 1LODHA DEVELOPERS LIMITED90/3, 91/2, 98/228-11-2022 00:00:00
MAHADEVSHREEM.M.CONSTRUCTION3308,9, 3311A31-01-2021 00:00:00
SAI PlazaSHREE SAI SHAKTI DEVELOPERS19 New Hissa No 1 6B And 15 Hissa No 1030-12-2023 00:00:00
SECTOR VI/E-6SHANTISTAR BUILDERS736 Bhayander Village30-09-2020 00:00:00
Shree Ambesh Complex And Ambesh BhavanShree Ambesh ConstructionThane, 40110531-07-2020 00:00:00
UNIQUE ORBIT-IUNIQUE SHANTI REALTORSS No. 401 H No 4B Off Village Ghoddev Mira Road East Thane 30-12-2020 00:00:00
Nida Amisha HeightsSAI KRUPA DEVELOPERSOld Survey No 21 Part And New Survey No 76 Hissa No 401-07-2026 00:00:00
DEEPAK APARTMENTSILVER & RASHI CONSTRUCTIONSNew 54 H No 6 And 725-12-2018 00:00:00
SHREENATH AVENUESHREENATH ENTERPRISES1031-03-2018 00:00:00
Sagar AccordM/ S. S A RealtyThane30-12-2021 00:00:00
Usha Kiran HeightsSai Sparsh DevelopersNear Vinayak Temple30-12-2022 00:00:00
N G Silver SpringRNA Builders (NG)3102P, 3111115-12-2018 00:00:00
ANNAPURNA JYOTIANNAPURNA ASSOCIATESSno 227 Hno 130-12-2021 00:00:00
BHAU PADMANN APARTMENTGujarat Land DevelopersSno 238 New Sno 187 Hsno 3 Navghar Village Mira Bhayandar Municipal Corporation31-12-2019 00:00:00
Ruheena AppartmentSairajdevelop401104, Thane31-12-2020 00:00:00
V. M. HeightsSwayam DevelopersThane, 40110731-12-2018 00:00:00
Heeru SadanHemant JainThane, 40110101-09-2018 00:00:00
Mini MarketHemant S JainOld Survey 136/1Pt New Survey 98/1 A And C31-12-2018 00:00:00
SKYWARDS REGENCYSKYWARDS VISION DEVELOPERS119 1N 1C 1D Mauje Davle Thane30-06-2020 00:00:00
Project Details
  • Project:
    Kakad Paradise Phase 2
  • Location:
  • Part Of 48/4 48/5 48/10 48/11 48/14 48/22 48/23 48/20 48/15 48/18 48/19 48/21 46/3 46/2 45/1
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2024
Developer Details

  • Developer:
    Kakad Housing Corporation
  • Phone:
  • Address:
  • Kakad House
Project RERA Details
MAHA REARA No: P51700006750
Project Type Others
RERA Project Status Ongoing
Architect Ajay Mane
Funding Bank AXIS BANK
Proposed Possession 30 Jun 2024
Revised Possession 30 Jun 2024
Extended Possession
Litigations No Litigations
Last Modified 17 Mar 2023
Last Retrived 13 Feb 2026
Kakad Paradise Phase 2 QR Code
Kakad Paradise Phase 2
MahaRERA - P51700006750
Apartment Details & Configuration
TypeArea
1 BHK36.53 Sq.mts. ( 393 Sq.ft. )
1 BHK37.59 Sq.mts. ( 405 Sq.ft. )
1 BHK38.66 Sq.mts. ( 416 Sq.ft. )
1 BHK40.32 Sq.mts. ( 434 Sq.ft. )
1 BHK42.56 Sq.mts. ( 458 Sq.ft. )
2 BHK50.05 Sq.mts. ( 539 Sq.ft. )
2 BHK51.63 Sq.mts. ( 556 Sq.ft. )
2 BHK52.31 Sq.mts. ( 563 Sq.ft. )
2 BHK53.83 Sq.mts. ( 579 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Kakad Paradise Phase 2last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work Not Started-Common For Phases 1 &Amp; 2
Community Buildings
Work Not Started-Common For Phases 1 &Amp; 2
Electrical Meter Room, Sub-Station, Receiving Station
Work Not Started.
Energy management
Work Not Started
Fire Protection And Fire Safety Requirements
Work Not Started
Landscaping & Tree Planting
Work Not Started
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Work Not Started. No Septic Tank
Solid Waste Management And Disposal
Work Not Started
Storm Water Drains
Work Not Started
Street Lighting
Work Not Started
Treatment And Disposal Of Sewage And Sullage Water
Work Not Started
Water Conservation, Rain water Harvesting
Work Not Started
Water Supply
Work Not Started
Buildings / Wings in Kakad Paradise Phase 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Kakad Paradise Phase 2 by Kakad Housing Corporationlast updated on 13 Feb 2026 as per information obtained from MARA RERA.

85112 Sq. ft.

Project Area

14187 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

200 apartments in total
Total
200
Booked
223
Available
-23

Saleable Area Statistics (Sq. ft.)

89228 Total
Total
89228
Booked
101887
Available
-12659
Total 200 apartments in project. 223 apartments booked. 111% apartments booked.
Total 89228 Sq.ft. saleable area. 101887 saleable area booked.
114% area booked.

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CJun 2024242020043
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.53 Sq.mts. ( 393 Sq.ft. )16
16 Booked100% Booked
100% Booked
1 BHK37.59 Sq.mts. ( 405 Sq.ft. )84
82 Booked97% Booked
97% Booked
1 BHK38.66 Sq.mts. ( 416 Sq.ft. )38
38 Booked100% Booked
100% Booked
1 BHK40.32 Sq.mts. ( 434 Sq.ft. )11
11 Booked100% Booked
100% Booked
149 total apartments / 147 apartments booked. 98% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DJun 2024241010043
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK42.56 Sq.mts. ( 458 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK50.05 Sq.mts. ( 539 Sq.ft. )11
36 Booked327% Booked
327% Booked
2 BHK51.63 Sq.mts. ( 556 Sq.ft. )19
19 Booked100% Booked
100% Booked
2 BHK52.31 Sq.mts. ( 563 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK53.83 Sq.mts. ( 579 Sq.ft. )16
16 Booked100% Booked
100% Booked
51 total apartments / 76 apartments booked. 149% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Kakad Housing Corporation
for Project
Kakad Paradise Phase 2
last updated on 13 Feb 2026 as per information obtained from MARA RERA.