2 Nos. of Common Basements80% completed
|
|
Common For Entire Layout As Per Afs |
3 Nos. of Common Podiums/E-deck81% completed
|
|
Common For Entire Layout As Per Afs |
Aggregate area of recreational Open Space
|
|
4365 Sq Mt Common To Entire Layout |
Club House,Fitness Centre Swimming pool & other Recreation areas27% completed
|
|
Common For Entire Layout As Per Afs |
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station73% completed
|
|
Electrical Meter Room And Sub Station Only |
Energy management30% completed
|
|
To Be Done Before Completion Of Whole Project |
Fire Protection And Fire Safety
Requirements70% completed
|
|
To Be Done Before Completion Of Whole Project |
Landscaping & Tree Planting78% completed
|
|
To Be Done Before Completion Of Whole Project |
|
|
Na |
|
|
To Be Done Before Completion Of Whole Project |
Sewerage (Chamber, Lines, Septic Tank , STP)75% completed
|
|
Stp- Common For Entire Layout |
Solid Waste Management And Disposal60% completed
|
|
To Be Done Before Completion Of Whole Project |
Storm Water Drains100% completed
|
|
To Be Done Before Completion Of Whole Project |
|
|
To Be Done Before Completion Of Whole Project |
Treatment And Disposal Of Sewage And Sullage Water
|
|
To Be Done Before Completion Of Whole Project |
Water Conservation, Rain water Harvesting80% completed
|
|
To Be Done Before Completion Of Whole Project |
Water Supply75% completed
|
|
Supply From Local Authority |