Project overview
NIVANTA is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000023225. NIVANTA is located at Survey No 1 Hissa No 2. This is a New being developed by YASHODEEP BUILDCON.
NIVANTA has 1 BHK & 2 BHK Apartments with carpet areas ranging from 314 to 505 Sq.ft. Carpet. The Project has total 150 of which 24 are currently available for sale.
NIVANTA is being developed on a total land area of 42948 Sq.ft. NIVANTA has 2 Wings / Towers Building No 1, A And B Wing,Building No 2, C And D Wing
| Project | Developer | Location | Possession |
| ARIHANT ANAIKA PHASE I | ARIHANT VATIKA REALTY PRIVATE LIMITED | 35-4 And 36-1 | 30-12-2018 00:00:00 |
| Mahaavir Majesty - Phase I | Mahaavir Impex | Survey No 1 | 31-12-2019 00:00:00 |
| DIVYA HEIGHTS | SAI HOMES DEVELOPERS | Plot No 30 | 31-12-2017 00:00:00 |
| ARIHANT ANAIKA PHASE II | ARIHANT VATIKA REALTY PRIVATE LIMITED | 35/04 And 36/01 | 30-12-2023 00:00:00 |
| GARDENIA | M/S KAMDHENU LIFESPACES | Survey No. 42/1, 42/2 | 30-12-2021 00:00:00 |
| SIDDHIVINAYAK GAURAV | GOPAL GHANSHYAMDAS GOYAL | Survey No 1 Hissa No 10 | 31-12-2026 00:00:00 |
| Rudra Rajendra | Rudra Developers | Survey No.66/6, 66/7 & 65/11 | 31-12-2026 00:00:00 |
| Riverside | Shristhi Developers | Survey No. 43/1/5 | 31-05-2026 00:00:00 |
| SIDDHIVINAYAK PRATIMA | SIDDHIVINAYAK HOMES | 1/6/10 | 30-12-2022 00:00:00 |
| QN GREENS PHASE 2 | QUALITAS NAMAN HOME MAKERS LLP | 1/3, 1/4, 1/5 And 1/7 | 30-06-2021 00:00:00 |
| Jvms Magnum | Jvm Spectrum Llp | Aegcj2pt2fmqp3a83i4k0dhywbhf0dnjproar96e0pa= | 31-12-2025 00:00:00 |
| NIVANTA | YASHODEEP BUILDCON | Survey No 1 Hissa No 2 | 30-12-2025 00:00:00 |
| SARVAM | Ashtvinayak Homes | 35/2, 35/3, 36/2 | 30-12-2026 00:00:00 |
| SIDDHIVINAYAK DARSHAN | YASHODEEP BUILDCON | Survey No 32 Hissa 12 | 31-12-2026 00:00:00 |
| JIJAI TULSI | SHUBHAM REALTY | Survey No 105/04, 105/05 & 106/01 | 31-12-2028 00:00:00 |
| SIDDHIVINAYAK SANKALP | YASHODEEP BUILDCON | Survey No 32 Hissa No 11 | 31-12-2027 00:00:00 |
| ARIHANT ANSHULA | ARIHANT AASHIYANA PRIVATE LIMITED | 1/1A, 67/4, 68/3B, 68/1 Plus 2, 68/6, 68/4 Plus 5, 67/1-1 | 30-12-2019 00:00:00 |
| Ramrai Kunj | Santosh Ramchandra Karavkar | 13 | 30-12-2022 00:00:00 |
| JIJAI COMPLEX | SHUBHAM BUILDERS & DEVELOPERS | 67/4 | 31-12-2018 00:00:00 |
| ANANT AURA | ANANT INFRA | Plot No. 51, Sec 26, Taloja | 30-06-2018 00:00:00 |
| IMPERIAL CREST | Suryakiran Enteprises | Plot No.62, Sector-26 | 31-03-2019 00:00:00 |
| QN GREENS PHASE 1 | QUALITAS NAMAN HOME MAKERS LLP | 1/3 | 31-12-2019 00:00:00 |
| Mahaavir Majesty - Phase II | Mahaavir Impex | Survey No. 66, Hissa No. 9 | 30-12-2022 00:00:00 |
| ARIHANT AMBER | ARIHANT VATIKA REALTY PRIVATE LIMITED | Survey No-2/2 And 2/5/B | 30-12-2026 00:00:00 |
| SIDDHIVINAYAK RIDDHIMA | SIDDHIVINAYAK HOMES | 1/9, 1/8/B, 1/1/7 | 30-12-2024 00:00:00 |
| HAPPY HOME | HAPPY LEISURE REALTIES LLP | 1/2 At Ghot, Panvel | 30-12-2024 00:00:00 |
| PRATIMA GOLD | SIDDHIVINAYAK HOMES | Survey No 1 Hissa No 13 | 30-06-2026 00:00:00 |
| QA Riverfront | RS Couture LLP | Survey No. 54/6 | 31-12-2027 00:00:00 |
| RUDRA KRISTINA-IV | SAI KRIPA | Survey No 2 | 31-12-2029 00:00:00 |
| Qa Riverfront 2 | Rs Buildcon | | 31-12-2030 00:00:00 |
| Riddhi Siddhi Vantara | Riddhi Siddhi Developers | | 31-12-2030 00:00:00 |
| Naman Solitaire | Bakliwal Infracon Private Limited | | 31-12-2029 00:00:00 |
| QN GREENS PHASE 3 | QUALITAS NAMAN HOME MAKERS LLP | 1/6/5, 1/6/6 | 30-12-2022 00:00:00 |
| Siddhivinayak Atulyam | DIVYADRISHTI BUILDCON PRIVATE LIMITED | Survey No 27 | 31-12-2027 00:00:00 |
| Rishikesh Aura | RISHIKESH ENTERPRISES | 11A | 31-12-2026 00:00:00 |
| Siddhivinayak Apartment | ROYAL REALTY | Survey No-41/A/42, 41/A/43 | 30-06-2026 00:00:00 |
| SIDDHIVINAYAK MAHIMA | SIDDHIVINAYAK HOMES | 32/9A, 32/9B | 30-12-2021 00:00:00 |
| SIDDHIVINAYAK GARIMA | SIDDHIVINAYAK HOMES | 30/0 | 31-12-2018 00:00:00 |
| Mahaavir Amber | OMPRAKASH BHANWARLAL CHHAJER | Survey No 111/11/1, 111/11/2 | 31-12-2027 00:00:00 |
| Imperial - Iv | Taj Construction | | 31-12-2029 00:00:00 |
| Omkara Pride Building 2 Wing C | Omkara Enterprises | S. No. 43/1/1 And S.No. 43/1/4 | 31-12-2028 00:00:00 |
-
Project:
NIVANTA
-
Location:
-
Survey No 1 Hissa No 2
-
Const. Stage:
New
-
Possession:
30 Dec 2025
-
Developer:
YASHODEEP BUILDCON
-
Phone:
-
Address:
-
Pratima
| MAHA REARA No: |
P52000023225 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Architect |
Adinath Patkar |
| Funding Bank |
PUNJAB AND SIND BANK |
| Proposed Possession |
30 Dec 2025 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
06 Dec 2019 |
| Last Retrived |
14 Feb 2026 |
NIVANTA QR Code
NIVANTA
MahaRERA - P52000023225
| Type | Area |
| 1 BHK | 29.19 Sq.mts. ( 314 Sq.ft. ) |
| 1 BHK | 30.04 Sq.mts. ( 323 Sq.ft. ) |
| 1 BHK | 30.27 Sq.mts. ( 326 Sq.ft. ) |
| 1 BHK | 31.12 Sq.mts. ( 335 Sq.ft. ) |
| 1 BHK | 32.2 Sq.mts. ( 347 Sq.ft. ) |
| 2 BHK | 43.01 Sq.mts. ( 463 Sq.ft. ) |
| 2 BHK | 43.64 Sq.mts. ( 470 Sq.ft. ) |
| 2 BHK | 43.87 Sq.mts. ( 472 Sq.ft. ) |
| 2 BHK | 44.09 Sq.mts. ( 475 Sq.ft. ) |
| 2 BHK | 44.72 Sq.mts. ( 481 Sq.ft. ) |
| 2 BHK | 46.88 Sq.mts. ( 505 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of NIVANTAlast updated on 14 Feb 2026 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space100% completed
|
|
Complete |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Wip |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Landscaping & Tree Planting100% completed
|
|
Complete |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Wip |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains100% completed
|
|
Complete |
|
|
|
Wip |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Na |
|
|
|
As Per Availability From Municipal Corporation |
Buildings / Wings in NIVANTA
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of NIVANTA by YASHODEEP BUILDCONlast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Apartments Statistics
150
apartments in total
Saleable Area Statistics (Sq. ft.)
55602
Total
Total 150 apartments in project. 126 apartments booked. 84% apartments booked.
Total 55602 Sq.ft. saleable area. 45445 saleable area booked.
82% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 1, A And B Wing | Dec 2024 | 6 | 1 | 0 | 1 | 0 | 0 | 16 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 29.19 Sq.mts. ( 314 Sq.ft. ) | 6 | |
| 1 BHK | 30.04 Sq.mts. ( 323 Sq.ft. ) | 20 | |
| 1 BHK | 30.27 Sq.mts. ( 326 Sq.ft. ) | 6 | |
| 1 BHK | 31.12 Sq.mts. ( 335 Sq.ft. ) | 6 | |
| 1 BHK | 32.2 Sq.mts. ( 347 Sq.ft. ) | 17 | |
| 2 BHK | 43.01 Sq.mts. ( 463 Sq.ft. ) | 2 | |
| 2 BHK | 43.64 Sq.mts. ( 470 Sq.ft. ) | 4 | |
| 2 BHK | 43.87 Sq.mts. ( 472 Sq.ft. ) | 2 | |
| 2 BHK | 44.09 Sq.mts. ( 475 Sq.ft. ) | 4 | |
| 2 BHK | 44.72 Sq.mts. ( 481 Sq.ft. ) | 4 | |
| 2 BHK | 46.88 Sq.mts. ( 505 Sq.ft. ) | 4 | |
75 total apartments / 66 apartments booked. 88% apartments booked. |
| Work Description in Building Building No 1, A And B Wing | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 2, C And D Wing | Dec 2024 | 6 | 1 | 0 | 1 | 0 | 0 | 16 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 29.19 Sq.mts. ( 314 Sq.ft. ) | 6 | |
| 1 BHK | 30.04 Sq.mts. ( 323 Sq.ft. ) | 20 | |
| 1 BHK | 30.27 Sq.mts. ( 326 Sq.ft. ) | 6 | |
| 1 BHK | 31.12 Sq.mts. ( 335 Sq.ft. ) | 6 | |
| 1 BHK | 32.2 Sq.mts. ( 347 Sq.ft. ) | 17 | |
| 2 BHK | 43.01 Sq.mts. ( 463 Sq.ft. ) | 2 | |
| 2 BHK | 43.64 Sq.mts. ( 470 Sq.ft. ) | 4 | |
| 2 BHK | 43.87 Sq.mts. ( 472 Sq.ft. ) | 2 | |
| 2 BHK | 44.09 Sq.mts. ( 475 Sq.ft. ) | 4 | |
| 2 BHK | 44.72 Sq.mts. ( 481 Sq.ft. ) | 4 | |
| 2 BHK | 46.88 Sq.mts. ( 505 Sq.ft. ) | 4 | |
75 total apartments / 60 apartments booked. 80% apartments booked. |
| Work Description in Building Building No 2, C And D Wing | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
YASHODEEP BUILDCON
for Project
NIVANTA
last updated on
14 Feb 2026 as per information obtained from MARA RERA.