Project overview
Pearl Residency - Wing-B, Residential Phase - Iii is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800006592. Pearl Residency - Wing-B, Residential Phase - Iii is located at Mumbai Suburban, 400053. This is a On-Going Project being developed by Giriraj Enterprises.
Pearl Residency - Wing-B, Residential Phase - Iii has 1 BHK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 284 to 756 Sq.ft. Carpet. The Project has total 35 of which 35 are currently available for sale.
Pearl Residency - Wing-B, Residential Phase - Iii is being developed on a total land area of 5597 Sq.ft. out of which 459 Sq.ft. i.e 8% is reserved for recreational purposes. Pearl Residency - Wing-B, Residential Phase - Iii has 1 Wings / Towers Pearl Residency - Wing-B, Residential Phase - Iii
Project | Developer | Location | Possession |
Krishna Chaitanya Rajbhavan Chsl | Ethics Infra Development Pvt. Ltd. | Maharashtra, Andheri East, Andheri East | 31-12-2018 00:00:00 |
Redevelopment Of Godi Kamgar Building C3 Wing B Skyvistas Bluez Phase Iii | Bharat Realty Venture Private Limited | D N Nagar Municipal School Road, D.N.Nagar, D.N.Nagar | 31-12-2021 00:00:00 |
-
Developer:
Giriraj Enterprises
-
Phone:
-
Address:
-
7Th Floor,, Pattathu Business Plaza,, Cst Road, Amar Brass, Santacruz East, 400098
MAHA REARA No: |
P51800006592 |
Project Type |
Residential |
RERA Project Status |
On-Going Project |
Architect |
Vastu Creations |
Funding Bank |
BANK OF BARODA |
Proposed Possession |
01 Aug 2022 |
Revised Possession |
01 Aug 2024 |
Extended Possession |
|
Litigations |
No Litigations |
Last Modified |
03 Feb 2024 |
Last Retrived |
14 Jan 2025 |
Pearl Residency - Wing-B, Residential Phase - Iii QR Code
Pearl Residency - Wing-B, Residential Phase - Iii
MahaRERA - P51800006592
Type | Area |
1 BHK | 26.39 Sq.mts. ( 284 Sq.ft. ) |
1 BHK | 27.55 Sq.mts. ( 297 Sq.ft. ) |
2 BHK | 49.12 Sq.mts. ( 529 Sq.ft. ) |
3 BHK | 58.27 Sq.mts. ( 627 Sq.ft. ) |
3 BHK | 70.27 Sq.mts. ( 756 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Pearl Residency - Wing-B, Residential Phase - Iiilast updated on 14 Jan 2025
as per information obtained from MARA RERA.
Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Work To Commence |
|
|
Work To Commence |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Work To Commence |
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Landscaping & Tree Planting
|
|
Na |
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
|
|
Work Partially Done |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains10% completed
|
|
Work Partially Done |
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Work To Commence |
|
|
Work To Commence |
Buildings / Wings in Pearl Residency - Wing-B, Residential Phase - Iii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pearl Residency - Wing-B, Residential Phase - Iii by Giriraj Enterpriseslast updated on 14 Jan 2025
as per information obtained from MARA RERA.
Apartments Statistics
35
apartments in total
Saleable Area Statistics (Sq. ft.)
17451
Total
Total 35 apartments in project. 0 apartments booked. 0% apartments booked.
Total 17451 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
Pearl Residency - Wing-B, Residential Phase - Iii | Jan 2024 | 8 | 1 | 0 | 1 | 0 | 0 | 1 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
1 BHK | 26.39 Sq.mts. ( 284 Sq.ft. ) | 7 | |
1 BHK | 27.55 Sq.mts. ( 297 Sq.ft. ) | 7 | |
2 BHK | 49.12 Sq.mts. ( 529 Sq.ft. ) | 7 | |
3 BHK | 58.27 Sq.mts. ( 627 Sq.ft. ) | 7 | |
3 BHK | 70.27 Sq.mts. ( 756 Sq.ft. ) | 7 | |
35 total apartments / 0 apartments booked. 0% apartments booked. |
Work Description in Building Pearl Residency - Wing-B, Residential Phase - Iii | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Overall Percentage of Completion of the work done For the entire Building /Wing | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Giriraj Enterprises
for Project
Pearl Residency - Wing-B, Residential Phase - Iii
last updated on
14 Jan 2025
as per information obtained from MARA RERA.
Name |
Company |
Location |
Mobile |
Designation |