Raunak City Sector Iv - D9 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700017488. Raunak City Sector Iv - D9 is located at Raunak City Road, Near Adharwadi Jail, Don Bosco School, Near Adharwadi Jail, Don Bosco School. This is a New Project being developed by Raunak Corporation.
Raunak City Sector Iv - D9 has 1 BHK Apartments with carpet areas ranging from 330 to 387 Sq.ft. Carpet. The Project has total 128 of which 0 are currently available for sale.
Raunak City Sector Iv - D9 is being developed on a total land area of 6283 Sq.ft. Raunak City Sector Iv - D9 has 1 Wings / Towers Raunak City - Sector Iv - D9
Project | Developer | Location | Possession |
-
Project:
Raunak City Sector Iv - D9
-
Location:
-
Raunak City Road, Near Adharwadi Jail, Don Bosco School, Near Adharwadi Jail, Don Bosco School
-
Const. Stage:
New Project
-
Possession:
30 Dec 2027
-
Developer:
Raunak Corporation
-
Phone:
-
Address:
-
Room No.26 3Rd Floor, Kilachand Building, 298 Princess Street, Near Parsi Dairy, Marine Lines, 400002
MAHA REARA No: |
P51700017488 |
Project Type |
Residential |
RERA Project Status |
New Project |
Architect |
Deisgn Consortium |
Funding Bank |
ICICI BANK |
Proposed Possession |
30 Dec 2027 |
Revised Possession |
|
Extended Possession |
|
Litigations |
Yes |
Last Modified |
07 Oct 2023 |
Last Retrived |
18 Jan 2025 |
Raunak City Sector Iv - D9 QR Code
Raunak City Sector Iv - D9
MahaRERA - P51700017488
Type | Area |
1 BHK | 30.69 Sq.mts. ( 330 Sq.ft. ) |
1 BHK | 35.66 Sq.mts. ( 384 Sq.ft. ) |
1 BHK | 35.99 Sq.mts. ( 387 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Raunak City Sector Iv - D9last updated on 18 Jan 2025
as per information obtained from MARA RERA.
Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
Community Buildings100% completed
|
|
Completed |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Completed |
Energy management100% completed
|
|
Completed |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Completed |
Landscaping & Tree Planting100% completed
|
|
Completed |
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Completed |
Solid Waste Management And Disposal100% completed
|
|
Completed |
Storm Water Drains100% completed
|
|
Completed |
Street Lighting100% completed
|
|
Completed |
Treatment And Disposal Of Sewage And Sullage Water100% completed
|
|
Completed |
Water Conservation, Rain water Harvesting100% completed
|
|
Completed |
Water Supply100% completed
|
|
Completed |
Buildings / Wings in Raunak City Sector Iv - D9
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Raunak City Sector Iv - D9 by Raunak Corporationlast updated on 18 Jan 2025
as per information obtained from MARA RERA.
Apartments Statistics
128
apartments in total
Saleable Area Statistics (Sq. ft.)
47148
Total
Total 128 apartments in project. 128 apartments booked. 100% apartments booked.
Total 47148 Sq.ft. saleable area. 47148 saleable area booked.
100% area booked.
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
Raunak City - Sector Iv - D9 | Dec 2026 | 23 | 1 | 0 | 1 | 0 | 0 | 14 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
1 BHK | 30.69 Sq.mts. ( 330 Sq.ft. ) | 40 | |
1 BHK | 35.66 Sq.mts. ( 384 Sq.ft. ) | 44 | |
1 BHK | 35.99 Sq.mts. ( 387 Sq.ft. ) | 44 | |
128 total apartments / 128 apartments booked. 100% apartments booked. |
Work Description in Building Raunak City - Sector Iv - D9 | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Overall Percentage of Completion of the work done For the entire Building /Wing | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Raunak Corporation
for Project
Raunak City Sector Iv - D9
last updated on
18 Jan 2025