Project overview

Sai River Palace is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000009277. Sai River Palace is located at Palghar, 401501. This is a On-Going Project being developed by Sai Universal Realtors &Amp; Developers Llp.

Sai River Palace has 1 BHK Apartments with carpet areas ranging from 295 to 326 Sq.ft. Carpet. The Project has total 121 of which 80 are currently available for sale.

Sai River Palace is being developed on a total land area of 144258 Sq.ft. out of which 15127 Sq.ft. i.e 10% is reserved for recreational purposes. Sai River Palace has 7 Wings / Towers Building No 1,Building No 2,Building No 3,Building No 4,Building No 6,Building No 7E,Building No 7F

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sai River Palace
  • Location:
  • Palghar, 401501
  • Const. Stage:
    On-Going Project
  • Possession:
    20 Dec 2018
Developer Details

  • Developer:
    Sai Universal Realtors &Amp; Developers Llp
  • Phone:
  • Address:
  • 130 Unit, Blue Rose Industrial Estate, Above Maruti Showroom, Next To Metro Mall, Borivali East, 400066
Project RERA Details
MAHA REARA No: P99000009277
Project Type Residential
RERA Project Status On-Going Project
Architect Mr Nishant Patil
Funding Bank Vijaya Bank
Proposed Possession 20 Dec 2018
Revised Possession 20 Dec 2021
Extended Possession 20 Dec 2022
Litigations No Litigations
Last Modified 13 Apr 2022
Last Retrived 13 Jan 2025
Sai River Palace QR Code
Sai River Palace
MahaRERA - P99000009277
Apartment Details & Configuration
TypeArea
Row House77.52 Sq.mts. ( 834 Sq.ft. )
1 BHK22.4 Sq.mts. ( 241 Sq.ft. )
1 BHK22.53 Sq.mts. ( 243 Sq.ft. )
StudioFlat121.45 Sq.mts. ( 231 Sq.ft. )
StudioFlat232.5 Sq.mts. ( 350 Sq.ft. )
StudioFlat335.2 Sq.mts. ( 379 Sq.ft. )
StudioFlat429.28 Sq.mts. ( 315 Sq.ft. )
StudioFlat532.65 Sq.mts. ( 351 Sq.ft. )
StudioFlat633.11 Sq.mts. ( 356 Sq.ft. )
Studio22.71 Sq.mts. ( 244 Sq.ft. )
Studio24.29 Sq.mts. ( 261 Sq.ft. )
1 BHK32.66 Sq.mts. ( 352 Sq.ft. )
2 BHK40.56 Sq.mts. ( 437 Sq.ft. )
2 BHK41.97 Sq.mts. ( 452 Sq.ft. )
Shop2.94 Sq.mts. ( 32 Sq.ft. )
Shop5.62 Sq.mts. ( 60 Sq.ft. )
1 BHK27.45 Sq.mts. ( 295 Sq.ft. )
1 BHK28.36 Sq.mts. ( 305 Sq.ft. )
1 BHK29.42 Sq.mts. ( 317 Sq.ft. )
1 BHK30.3 Sq.mts. ( 326 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sai River Palacelast updated on 13 Jan 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Club House Will Be Provided Before Oc
Electrical Meter Room, Sub-Station, Receiving Station
Will Be Provided Before Oc
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Will Be Provided Before Oc
Open Parking
Will Be Provided Before Oc
Sewerage (Chamber, Lines, Septic Tank , STP)
Will Be Provided Before Oc
Solid Waste Management And Disposal
Na
Storm Water Drains
Will Be Provided Before Oc
Street Lighting
Will Be Provided Before Oc
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Will Be Provided Before Oc
Water Supply100% completed
95% Complete
Borewell Has Been Completed
Buildings / Wings in Sai River Palace
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sai River Palace by Sai Universal Realtors &Amp; Developers Llplast updated on 13 Jan 2025 as per information obtained from MARA RERA.

144258 Sq. ft.

Project Area

15127 Sq. ft.

Recreational Open Space

Total 7

Wings / Towers in Project

Apartments Statistics

121 apartments in total
Total
121
Booked
41
Available
80

Saleable Area Statistics (Sq. ft.)

49360 Total
Total
49360
Booked
25483
Available
23877
Total 121 apartments in project. 41 apartments booked. 33% apartments booked.
Total 49360 Sq.ft. saleable area. 25483 saleable area booked.
52% area booked.

Building No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1Jan 19002011071
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Row House77.52 Sq.mts. ( 834 Sq.ft. )7
7 Booked100% Booked
100% Booked
7 total apartments / 7 apartments booked. 100% apartments booked.
Work Description in Building Building No 1Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress51% done
51% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress60% done
60% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2Jan 19002101081
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Row House77.52 Sq.mts. ( 834 Sq.ft. )8
8 Booked100% Booked
100% Booked
8 total apartments / 8 apartments booked. 100% apartments booked.
Work Description in Building Building No 2Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress75% done
75% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3Jan 19002101071
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Row House77.52 Sq.mts. ( 834 Sq.ft. )7
7 Booked100% Booked
100% Booked
7 total apartments / 7 apartments booked. 100% apartments booked.
Work Description in Building Building No 3Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress25% done
25% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress50% done
50% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4Jan 19005100050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.4 Sq.mts. ( 241 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK22.53 Sq.mts. ( 243 Sq.ft. )16
None Booked0% Booked
0% Booked
StudioFlat121.45 Sq.mts. ( 231 Sq.ft. )1
None Booked0% Booked
0% Booked
StudioFlat232.5 Sq.mts. ( 350 Sq.ft. )2
1 Booked50% Booked
50% Booked
StudioFlat335.2 Sq.mts. ( 379 Sq.ft. )1
1 Booked100% Booked
100% Booked
StudioFlat429.28 Sq.mts. ( 315 Sq.ft. )4
None Booked0% Booked
0% Booked
StudioFlat532.65 Sq.mts. ( 351 Sq.ft. )8
2 Booked25% Booked
25% Booked
StudioFlat633.11 Sq.mts. ( 356 Sq.ft. )4
2 Booked50% Booked
50% Booked
40 total apartments / 6 apartments booked. 15% apartments booked.
Work Description in Building Building No 4Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Building No 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 6Jan 190051000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK35.2 Sq.mts. ( 379 Sq.ft. )5
5 Booked100% Booked
100% Booked
Studio22.71 Sq.mts. ( 244 Sq.ft. )4
None Booked0% Booked
0% Booked
Studio24.29 Sq.mts. ( 261 Sq.ft. )10
2 Booked20% Booked
20% Booked
19 total apartments / 7 apartments booked. 36% apartments booked.
Work Description in Building Building No 6Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress36% done
36% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress50% done
50% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress90% done
90% Booked

Building No 7E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 7EJan 19005101051
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.66 Sq.mts. ( 352 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK40.56 Sq.mts. ( 437 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK41.97 Sq.mts. ( 452 Sq.ft. )16
5 Booked31% Booked
31% Booked
Shop2.94 Sq.mts. ( 32 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop5.62 Sq.mts. ( 60 Sq.ft. )2
None Booked0% Booked
0% Booked
22 total apartments / 5 apartments booked. 22% apartments booked.
Work Description in Building Building No 7ECompletion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 7F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 7FJan 19005101051
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.45 Sq.mts. ( 295 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK28.36 Sq.mts. ( 305 Sq.ft. )8
1 BHK29.42 Sq.mts. ( 317 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.3 Sq.mts. ( 326 Sq.ft. )8
None Booked0% Booked
0% Booked
18 total apartments / 1 apartments booked. 5% apartments booked.
Work Description in Building Building No 7FCompletion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Sai Universal Realtors &Amp; Developers Llp
for Project
Sai River Palace
last updated on 13 Jan 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation