Project overview

Samruddhi Evergreens Phase-4C is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700009156. Samruddhi Evergreens Phase-4C is located at Thane, 421503, -. This is a On-Going Project being developed by Poddar Housing And Development Limited.

Samruddhi Evergreens Phase-4C has 1 BHK Apartments with carpet areas ranging from 334 to 334 Sq.ft. Carpet. The Project has total 114 of which 21 are currently available for sale.

Samruddhi Evergreens Phase-4C is being developed on a total land area of 42927 Sq.ft. Samruddhi Evergreens Phase-4C has 7 Wings / Towers 140,141,142,143,144,145,148

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Samruddhi Evergreens Phase-4C
  • Location:
  • Thane, 421503, -
  • Const. Stage:
    On-Going Project
  • Possession:
    31 Mar 2020
Developer Details

  • Developer:
    Poddar Housing And Development Limited
  • Phone:
  • Address:
  • Unit No. 3-5, Poddar Group Building, 126 N M Joshi Marg, Mathuradas Mill Compound, Lower Parel West, 400013
Project RERA Details
MAHA REARA No: P51700009156
Project Type Others
RERA Project Status On-Going Project
Funding Bank HDFC BANK LTD
Proposed Possession 31 Mar 2020
Revised Possession 31 Mar 2020
Extended Possession 27 Dec 2024
Litigations No Litigations
Last Modified 02 Feb 2024
Last Retrived 28 Jul 2025
Samruddhi Evergreens Phase-4C QR Code
Samruddhi Evergreens Phase-4C
MahaRERA - P51700009156
Apartment Details & Configuration
TypeArea
1 BHK31 Sq.mts. ( 334 Sq.ft. )
SHOP23 Sq.mts. ( 248 Sq.ft. )
SHOP24 Sq.mts. ( 258 Sq.ft. )
2 BHK48 Sq.mts. ( 517 Sq.ft. )
2 BHK47 Sq.mts. ( 506 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Samruddhi Evergreens Phase-4Clast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Common For Entire Project
Community Buildings100% completed
95% Complete
Common For Entire Project
Electrical Meter Room, Sub-Station, Receiving Station80% completed
80% Complete
Under Progress
Energy management
Na
Fire Protection And Fire Safety Requirements
Fire Extinguisher For G+3 Building
Landscaping & Tree Planting
Common For Entire Project
Open Parking
Common
Sewerage (Chamber, Lines, Septic Tank , STP)85% completed
85% Complete
Stp Ready For Entire Project
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Under Progress
Street Lighting85% completed
85% Complete
Under Progress
Treatment And Disposal Of Sewage And Sullage Water80% completed
80% Complete
Under Progress
Water Conservation, Rain water Harvesting100% completed
95% Complete
Rain Water Harvesting
Water Supply85% completed
85% Complete
Under Progress
Buildings / Wings in Samruddhi Evergreens Phase-4C
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Samruddhi Evergreens Phase-4C by Poddar Housing And Development Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

42927 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 7

Wings / Towers in Project

Apartments Statistics

114 apartments in total
Total
114
Booked
93
Available
21

Saleable Area Statistics (Sq. ft.)

48772 Total
Total
48772
Booked
40021
Available
8751
Total 114 apartments in project. 93 apartments booked. 81% apartments booked.
Total 48772 Sq.ft. saleable area. 40021 saleable area booked.
82% area booked.

140

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
140Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31 Sq.mts. ( 334 Sq.ft. )12
12 Booked100% Booked
100% Booked
SHOP23 Sq.mts. ( 248 Sq.ft. )5
None Booked0% Booked
0% Booked
17 total apartments / 12 apartments booked. 70% apartments booked.
Work Description in Building 140Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

141

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
141Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31 Sq.mts. ( 334 Sq.ft. )12
12 Booked100% Booked
100% Booked
SHOP24 Sq.mts. ( 258 Sq.ft. )5
3 Booked60% Booked
60% Booked
17 total apartments / 15 apartments booked. 88% apartments booked.
Work Description in Building 141Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

142

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
142Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48 Sq.mts. ( 517 Sq.ft. )16
8 Booked50% Booked
50% Booked
16 total apartments / 8 apartments booked. 50% apartments booked.
Work Description in Building 142Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

143

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
143Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48 Sq.mts. ( 517 Sq.ft. )16
16 Booked100% Booked
100% Booked
16 total apartments / 16 apartments booked. 100% apartments booked.
Work Description in Building 143Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

144

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
144Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48 Sq.mts. ( 517 Sq.ft. )16
16 Booked100% Booked
100% Booked
16 total apartments / 16 apartments booked. 100% apartments booked.
Work Description in Building 144Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

145

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
145Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47 Sq.mts. ( 506 Sq.ft. )16
11 Booked68% Booked
68% Booked
16 total apartments / 11 apartments booked. 68% apartments booked.
Work Description in Building 145Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

148

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
148Mar 20204100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31 Sq.mts. ( 334 Sq.ft. )16
15 Booked93% Booked
93% Booked
16 total apartments / 15 apartments booked. 93% apartments booked.
Work Description in Building 148Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Poddar Housing And Development Limited
for Project
Samruddhi Evergreens Phase-4C
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation