Project overview
Sunrise Orlem 2B Phase 3 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800006843. Sunrise Orlem 2B Phase 3 is located at Mumbai Suburban, 400097. This is a On-Going Project being developed by Dhaval Housing Aop.
Sunrise Orlem 2B Phase 3 has 2 BHK Type 1 Apartments with carpet areas ranging from 861 to 861 Sq.ft. Carpet. The Project has total 42 of which 1 are currently available for sale.
Sunrise Orlem 2B Phase 3 is being developed on a total land area of 2421 Sq.ft. out of which 7911 Sq.ft. i.e 327% is reserved for recreational purposes. Sunrise Orlem 2B Phase 3 has 1 Wings / Towers Sunrise Orlem 2B
Project | Developer | Location | Possession |
Mauli Omkar | Mauli Sai Developers Pvt Ltd | Vaishet Pada, Triveni Nagar, Triveni Nagar | 08-07-2021 00:00:00 |
Mauli Pride | Mauli Sai Developers Pvt Ltd | Daftary Road, Kurar Village, Kurar Village | 08-07-2020 00:00:00 |
-
Project:
Sunrise Orlem 2B Phase 3
-
Location:
-
Mumbai Suburban, 400097
-
Const. Stage:
On-Going Project
-
Possession:
31 Dec 2020
-
Developer:
Dhaval Housing Aop
-
Phone:
-
Address:
-
401, Centerpoint, Jn. Of Juhu Tara Rd &Amp; Sv Rd, Above Standard Chartered Bank, Santacruz West, 400054
MAHA REARA No: |
P51800006843 |
Project Type |
Residential |
RERA Project Status |
On-Going Project |
Architect |
Design Studio Ahmedabad |
Funding Bank |
The Bharat Cooperative Bank Ltd |
Proposed Possession |
31 Dec 2020 |
Revised Possession |
30 Jun 2021 |
Extended Possession |
31 Dec 2023 |
Litigations |
Yes |
Last Modified |
11 Jan 2024 |
Last Retrived |
16 Jan 2025 |
Sunrise Orlem 2B Phase 3 QR Code
Sunrise Orlem 2B Phase 3
MahaRERA - P51800006843
Type | Area |
2 BHK Type 1 | 79.96 Sq.mts. ( 861 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Sunrise Orlem 2B Phase 3last updated on 16 Jan 2025
as per information obtained from MARA RERA.
Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space100% completed
|
|
To Be Completed Before Completion Of Tower |
|
|
To Be Finished Before Hand Over Of Layout |
Electrical Meter Room, Sub-Station, Receiving Station95% completed
|
|
To Be Completed Before Completion Of Tower |
|
|
Common For The Layout |
Fire Protection And Fire Safety
Requirements95% completed
|
|
Na |
Landscaping & Tree Planting90% completed
|
|
Common For The Layout |
|
|
To Be Completed When Handing Over Layout |
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
|
|
External Sewer Line Laid |
Solid Waste Management And Disposal
|
|
To Be Handed Over Before Possession |
Storm Water Drains95% completed
|
|
Common For The Layout |
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Na |
Water Supply95% completed
|
|
To Be Handed Before Possession |
Buildings / Wings in Sunrise Orlem 2B Phase 3
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sunrise Orlem 2B Phase 3 by Dhaval Housing Aoplast updated on 16 Jan 2025
as per information obtained from MARA RERA.
Apartments Statistics
42
apartments in total
Saleable Area Statistics (Sq. ft.)
36149
Total
Total 42 apartments in project. 41 apartments booked. 97% apartments booked.
Total 36149 Sq.ft. saleable area. 35288 saleable area booked.
98% area booked.
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
Sunrise Orlem 2B | Jun 2022 | 23 | 1 | 0 | 1 | 0 | 0 | 42 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
2 BHK Type 1 | 79.96 Sq.mts. ( 861 Sq.ft. ) | 42 | |
42 total apartments / 41 apartments booked. 97% apartments booked. |
Work Description in Building Sunrise Orlem 2B | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Overall Percentage of Completion of the work done For the entire Building /Wing | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Dhaval Housing Aop
for Project
Sunrise Orlem 2B Phase 3
last updated on
16 Jan 2025
as per information obtained from MARA RERA.
Name |
Company |
Location |
Mobile |
Designation |