Project overview

Sunteck West World 1, Tivri, Naigaon East is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000017606. Sunteck West World 1, Tivri, Naigaon East is located at Tivri, Tivri. This is a New Project being developed by Sunteck Realty Limited.

Sunteck West World 1, Tivri, Naigaon East has 1 BHK & 2 BHK Apartments with carpet areas ranging from 285 to 450 Sq.ft. Carpet. The Project has total 1764 of which 26 are currently available for sale.

Sunteck West World 1, Tivri, Naigaon East is being developed on a total land area of 238730 Sq.ft. out of which 30115 Sq.ft. i.e 13% is reserved for recreational purposes. Sunteck West World 1, Tivri, Naigaon East has 5 Wings / Towers Building No 1,Building No 2,Building No 3,Building No 4,Building No 5

ProjectDeveloperLocationPossession
Nakshatra Greens - Phase IiJsb Buildcon LlpPalghar, 40130431-12-2018 00:00:00
Ornate Galaxy Phase ISai Ornate DevelopersStation Road, Naigaon East, Naigaon East30-09-2017 00:00:00
Rashmi Star City Phase 4Rashmi Realty Builders Pvt LtdNaigaon East, Naigaon East30-06-2021 00:00:00
Navkar City Phase Ii Part INavkar Estate And Homes Pvt LtdRoad, Naigaon, Naigaon31-12-2017 00:00:00
Navkar City Phase Ii Part 3Navkar Estate And Homes Pvt LtdNaigaon East, Naigaon, Naigaon31-12-2017 00:00:00
Project Details
  • Project:
    Sunteck West World 1, Tivri, Naigaon East
  • Location:
  • Tivri, Tivri
  • Const. Stage:
    New Project
  • Possession:
    30 Sep 2023
Developer Details

  • Developer:
    Sunteck Realty Limited
  • Phone:
  • Address:
  • 5Th Floor, Sunteck Centre, 37-40 Subhash Road, Next To Sbi, Vile Parle East, 400057
Project RERA Details
MAHA REARA No: P99000017606
Project Type Residential
RERA Project Status New Project
Funding Bank Axis Bank Limited
Proposed Possession 30 Sep 2023
Revised Possession
Extended Possession
Litigations Yes
Last Modified 04 Oct 2023
Last Retrived 13 Jan 2025
Sunteck West World 1, Tivri, Naigaon East QR Code
Sunteck West World 1, Tivri, Naigaon East
MahaRERA - P99000017606
Apartment Details & Configuration
TypeArea
1 BHK26.46 Sq.mts. ( 285 Sq.ft. )
2 BHK41.76 Sq.mts. ( 450 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sunteck West World 1, Tivri, Naigaon Eastlast updated on 13 Jan 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work Not Started
Community Buildings100% completed
95% Complete
Work Completed
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Work Completed
Energy management100% completed
95% Complete
Work Completed
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Work Completed
Landscaping & Tree Planting100% completed
95% Complete
Work Completed
Open Parking
Work Not Started
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Work Completed
Solid Waste Management And Disposal100% completed
95% Complete
Work Completed
Storm Water Drains100% completed
95% Complete
Work Completed
Street Lighting100% completed
95% Complete
Work Completed
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Work Completed
Water Conservation, Rain water Harvesting100% completed
95% Complete
Work Completed
Water Supply100% completed
95% Complete
Work Completed
Buildings / Wings in Sunteck West World 1, Tivri, Naigaon East
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sunteck West World 1, Tivri, Naigaon East by Sunteck Realty Limitedlast updated on 13 Jan 2025 as per information obtained from MARA RERA.

238730 Sq. ft.

Project Area

30115 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

1764 apartments in total
Total
1764
Booked
1738
Available
26

Saleable Area Statistics (Sq. ft.)

603863 Total
Total
603863
Booked
595799
Available
8064
Total 1764 apartments in project. 1738 apartments booked. 98% apartments booked.
Total 603863 Sq.ft. saleable area. 595799 saleable area booked.
99% area booked.

Building No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1Dec 2021221010016
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.46 Sq.mts. ( 285 Sq.ft. )246
243 Booked98% Booked
98% Booked
2 BHK41.76 Sq.mts. ( 450 Sq.ft. )132
132 Booked100% Booked
100% Booked
378 total apartments / 375 apartments booked. 99% apartments booked.
Work Description in Building Building No 1Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2Sep 2022221010017
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.46 Sq.mts. ( 285 Sq.ft. )246
243 Booked98% Booked
98% Booked
2 BHK41.76 Sq.mts. ( 450 Sq.ft. )132
132 Booked100% Booked
100% Booked
378 total apartments / 375 apartments booked. 99% apartments booked.
Work Description in Building Building No 2Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3Dec 2021221010016
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.46 Sq.mts. ( 285 Sq.ft. )246
243 Booked98% Booked
98% Booked
2 BHK41.76 Sq.mts. ( 450 Sq.ft. )132
131 Booked99% Booked
99% Booked
378 total apartments / 374 apartments booked. 98% apartments booked.
Work Description in Building Building No 3Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4Sep 2022221010017
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.46 Sq.mts. ( 285 Sq.ft. )246
235 Booked95% Booked
95% Booked
2 BHK41.76 Sq.mts. ( 450 Sq.ft. )132
132 Booked100% Booked
100% Booked
378 total apartments / 367 apartments booked. 97% apartments booked.
Work Description in Building Building No 4Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 5Sep 2022221010011
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.46 Sq.mts. ( 285 Sq.ft. )164
162 Booked98% Booked
98% Booked
2 BHK41.76 Sq.mts. ( 450 Sq.ft. )88
85 Booked96% Booked
96% Booked
252 total apartments / 247 apartments booked. 98% apartments booked.
Work Description in Building Building No 5Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Sunteck Realty Limited
for Project
Sunteck West World 1, Tivri, Naigaon East
last updated on 13 Jan 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation