Project overview
The Palms is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700000006. The Palms is located at Sector-50, Nerul, Nerul. This is a On-Going Project being developed by Metro Development.
The Palms has 2 BHK, 3 BHK & 5 BHK & more Apartments with carpet areas ranging from 1557 to 854 Sq.ft. Carpet. The Project has total 79 of which 0 are currently available for sale.
The Palms is being developed on a total land area of 39612 Sq.ft. The Palms has 1 Wings / Towers The Palms
Project | Developer | Location | Possession |
-
Project:
The Palms
-
Location:
-
Sector-50, Nerul, Nerul
-
Const. Stage:
On-Going Project
-
Possession:
31 Dec 2018
-
Developer:
Metro Development
-
Phone:
-
Address:
-
301/302, The Ambience Court, Plot No-2, Vashi Rto, Sector-19D, 400703
MAHA REARA No: |
P51700000006 |
Project Type |
Residential |
RERA Project Status |
On-Going Project |
Architect |
Amit N .Patil Architects |
Funding Bank |
HDFC Bank |
Proposed Possession |
31 Dec 2018 |
Revised Possession |
31 Mar 2019 |
Extended Possession |
|
Litigations |
Yes |
Last Modified |
01 Nov 2022 |
Last Retrived |
16 Jan 2025 |
The Palms QR Code
The Palms
MahaRERA - P51700000006
Type | Area |
2 BHK | 44.98 Sq.mts. ( 484 Sq.ft. ) |
2 BHK | 46.36 Sq.mts. ( 499 Sq.ft. ) |
2 BHK | 46.37 Sq.mts. ( 499 Sq.ft. ) |
2 BHK | 46.65 Sq.mts. ( 502 Sq.ft. ) |
2 BHK | 48.45 Sq.mts. ( 522 Sq.ft. ) |
2 BHK | 48.81 Sq.mts. ( 525 Sq.ft. ) |
3 BHK | 69.01 Sq.mts. ( 743 Sq.ft. ) |
3 BHK | 69.35 Sq.mts. ( 746 Sq.ft. ) |
3 BHK | 71.4 Sq.mts. ( 769 Sq.ft. ) |
3 BHK | 72.13 Sq.mts. ( 776 Sq.ft. ) |
3 BHK | 72.4 Sq.mts. ( 779 Sq.ft. ) |
3 BHK | 73.2 Sq.mts. ( 788 Sq.ft. ) |
3 BHK | 74.08 Sq.mts. ( 797 Sq.ft. ) |
3 BHK | 74.62 Sq.mts. ( 803 Sq.ft. ) |
3 BHK | 76.29 Sq.mts. ( 821 Sq.ft. ) |
3 BHK | 79.36 Sq.mts. ( 854 Sq.ft. ) |
5 BHK & more | 144.66 Sq.mts. ( 1557 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of The Palmslast updated on 16 Jan 2025
as per information obtained from MARA RERA.
Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Civil Work Completed |
|
|
In Progress |
Electrical Meter Room, Sub-Station, Receiving Station60% completed
|
|
In Progress |
|
|
In Later Scope Of Work |
Fire Protection And Fire Safety
Requirements90% completed
|
|
In Progress |
Landscaping & Tree Planting50% completed
|
|
Completed |
|
|
In Progress |
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
|
|
Chamber Line Work In Progress |
Solid Waste Management And Disposal
|
|
In Later Scope Of Work |
Storm Water Drains100% completed
|
|
S.T/Stp Not Required |
|
|
Iin Progress |
SWIMMING POOL20% completed
|
|
Civil Work Completed |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting90% completed
|
|
In Later Scope Of Work |
Water Supply50% completed
|
|
In Progress |
Buildings / Wings in The Palms
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of The Palms by Metro Developmentlast updated on 16 Jan 2025
as per information obtained from MARA RERA.
Apartments Statistics
79
apartments in total
Saleable Area Statistics (Sq. ft.)
54778
Total
Total 79 apartments in project. 79 apartments booked. 100% apartments booked.
Total 54778 Sq.ft. saleable area. 54778 saleable area booked.
100% area booked.
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
The Palms | Mar 2019 | 14 | 1 | 1 | 1 | 1 | 13 | 159 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
2 BHK | 44.98 Sq.mts. ( 484 Sq.ft. ) | 1 | |
2 BHK | 46.36 Sq.mts. ( 499 Sq.ft. ) | 1 | |
2 BHK | 46.37 Sq.mts. ( 499 Sq.ft. ) | 1 | |
2 BHK | 46.65 Sq.mts. ( 502 Sq.ft. ) | 2 | |
2 BHK | 48.45 Sq.mts. ( 522 Sq.ft. ) | 18 | |
2 BHK | 48.81 Sq.mts. ( 525 Sq.ft. ) | 10 | |
3 BHK | 69.01 Sq.mts. ( 743 Sq.ft. ) | 1 | |
3 BHK | 69.35 Sq.mts. ( 746 Sq.ft. ) | 1 | |
3 BHK | 71.4 Sq.mts. ( 769 Sq.ft. ) | 18 | |
3 BHK | 72.13 Sq.mts. ( 776 Sq.ft. ) | 1 | |
3 BHK | 72.4 Sq.mts. ( 779 Sq.ft. ) | 1 | |
3 BHK | 73.2 Sq.mts. ( 788 Sq.ft. ) | 2 | |
3 BHK | 74.08 Sq.mts. ( 797 Sq.ft. ) | 9 | |
3 BHK | 74.62 Sq.mts. ( 803 Sq.ft. ) | 9 | |
3 BHK | 76.29 Sq.mts. ( 821 Sq.ft. ) | 1 | |
3 BHK | 79.36 Sq.mts. ( 854 Sq.ft. ) | 1 | |
5 BHK & more | 144.66 Sq.mts. ( 1557 Sq.ft. ) | 2 | |
79 total apartments / 79 apartments booked. 100% apartments booked. |
Work Description in Building The Palms | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Metro Development
for Project
The Palms
last updated on
16 Jan 2025
as per information obtained from MARA RERA.
Name |
Company |
Location |
Mobile |
Designation |