Project overview

Vaikunth Cluster 4A is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700005256. Vaikunth Cluster 4A is located at 100/24-30,100/31A,31B. This is a New being developed by Piramal Estate Private Limited.

Vaikunth Cluster 4A has 2 BHK Apartments with carpet areas ranging from 495 to 517 Sq.ft. Carpet. The Project has total 583 of which 18 are currently available for sale.

Vaikunth Cluster 4A is being developed on a total land area of 36826 Sq.ft. out of which 1789 Sq.ft. i.e 5% is reserved for recreational purposes. Vaikunth Cluster 4A has 2 Wings / Towers Vama,Vyan

ProjectDeveloperLocationPossession
Sai ApartmentsGajanan Kotkar & Nandini Kotkar5931-12-2018 00:00:00
New Kirtikar ProposedChaturthi Developers40060201-07-2025 00:00:00
Shanti KunjShreyas Enterprises616,617,61831-12-2017 00:00:00
Project Details
  • Project:
    Vaikunth Cluster 4A
  • Location:
  • 100/24-30,100/31A,31B
  • Const. Stage:
    New
  • Possession:
    31 Jul 2024
Developer Details

  • Developer:
    Piramal Estate Private Limited
  • Phone:
  • Address:
  • Piramal Tower
Project RERA Details
MAHA REARA No: P51700005256
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank HDFC BANK
Proposed Possession 31 Jul 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 17 Nov 2023
Last Retrived 26 Jul 2025
Vaikunth Cluster 4A QR Code
Vaikunth Cluster 4A
MahaRERA - P51700005256
Apartment Details & Configuration
TypeArea
2 BHK47 Sq.mts. ( 506 Sq.ft. )
2 BHK48 Sq.mts. ( 517 Sq.ft. )
2 BHK49 Sq.mts. ( 527 Sq.ft. )
2 BHK46 Sq.mts. ( 495 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Vaikunth Cluster 4Alast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work Yet To Be Started
Community Buildings90% completed
90% Complete
A Part Of A Larger Layout
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
As Per Statutory Requirements
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Statutory Requirements
Landscaping & Tree Planting60% completed
60% Complete
Work Yet To Be Started
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Stp As Part Of Larger Layout
Solid Waste Management And Disposal100% completed
95% Complete
Work Yet To Be Started
Storm Water Drains100% completed
95% Complete
As Per Statutory Requirements
Street Lighting50% completed
50% Complete
Work Yet To Be Started
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Work Yet To Be Started
Water Conservation, Rain water Harvesting100% completed
95% Complete
As Per Statutory Requirements
Water Supply100% completed
95% Complete
Work Yet To Be Started
Buildings / Wings in Vaikunth Cluster 4A
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Vaikunth Cluster 4A by Piramal Estate Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

36826 Sq. ft.

Project Area

1789 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

583 apartments in total
Total
583
Booked
565
Available
18

Saleable Area Statistics (Sq. ft.)

296247 Total
Total
296247
Booked
287119
Available
9128
Total 583 apartments in project. 565 apartments booked. 96% apartments booked.
Total 296247 Sq.ft. saleable area. 287119 saleable area booked.
97% area booked.

Vama

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
VamaJul 20244011050292
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47 Sq.mts. ( 506 Sq.ft. )189
183 Booked96% Booked
96% Booked
2 BHK48 Sq.mts. ( 517 Sq.ft. )94
93 Booked98% Booked
98% Booked
2 BHK49 Sq.mts. ( 527 Sq.ft. )11
10 Booked90% Booked
90% Booked
294 total apartments / 286 apartments booked. 97% apartments booked.
Work Description in Building VamaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress96% done
96% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress96% done
96% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress91% done
91% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress91% done
91% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress85% done
85% Booked
Sanitary Fittings within the flats / premises
work-in-progress85% done
85% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress87% done
87% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress87% done
87% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Vyan

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
VyanJul 20244011050290
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK46 Sq.mts. ( 495 Sq.ft. )48
47 Booked97% Booked
97% Booked
2 BHK47 Sq.mts. ( 506 Sq.ft. )188
179 Booked95% Booked
95% Booked
2 BHK48 Sq.mts. ( 517 Sq.ft. )53
53 Booked100% Booked
100% Booked
289 total apartments / 279 apartments booked. 96% apartments booked.
Work Description in Building VyanCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress96% done
96% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress96% done
96% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress33% done
33% Booked
Sanitary Fittings within the flats / premises
work-in-progress33% done
33% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress93% done
93% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress93% done
93% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Piramal Estate Private Limited
for Project
Vaikunth Cluster 4A
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation