Project overview
Wing B Of Composite Building No 1 Imperial Edge is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900000723. Wing B Of Composite Building No 1 Imperial Edge is located at B.B. Nakashe Marg, Tardeo, Tardeo. This is a On-Going Project being developed by Sd Corporation Private Limited.
Wing B Of Composite Building No 1 Imperial Edge has 3 BHK Apartments with carpet areas ranging from 1541 to 1541 Sq.ft. Carpet. The Project has total 46 of which 6 are currently available for sale.
Wing B Of Composite Building No 1 Imperial Edge is being developed on a total land area of 13529 Sq.ft. Wing B Of Composite Building No 1 Imperial Edge has 1 Wings / Towers The Imperial Edge
Project | Developer | Location | Possession |
-
Project:
Wing B Of Composite Building No 1 Imperial Edge
-
Location:
-
B.B. Nakashe Marg, Tardeo, Tardeo
-
Const. Stage:
On-Going Project
-
Possession:
31 Mar 2019
-
Developer:
Sd Corporation Private Limited
-
Phone:
-
Address:
-
70, 3Rd Floor, Sp Centre, Nagindas Master Road, Above Mahanagar Co-Operative Bank Ltd., Fort, 400023
MAHA REARA No: |
P51900000723 |
Project Type |
Residential |
RERA Project Status |
On-Going Project |
Architect |
Vision |
Funding Bank |
HDFC Bank Ltd |
Proposed Possession |
31 Mar 2019 |
Revised Possession |
30 Dec 2021 |
Extended Possession |
|
Litigations |
No Litigations |
Last Modified |
20 Dec 2022 |
Last Retrived |
14 Jan 2025 |
Wing B Of Composite Building No 1 Imperial Edge QR Code
Wing B Of Composite Building No 1 Imperial Edge
MahaRERA - P51900000723
Type | Area |
3 BHK | 143.14 Sq.mts. ( 1541 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Wing B Of Composite Building No 1 Imperial Edgelast updated on 14 Jan 2025
as per information obtained from MARA RERA.
Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Done |
Energy management100% completed
|
|
Done |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Done |
Landscaping & Tree Planting97% completed
|
|
Work In Progress |
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Done |
Solid Waste Management And Disposal100% completed
|
|
Done |
Storm Water Drains100% completed
|
|
Done |
Street Lighting100% completed
|
|
Done |
Treatment And Disposal Of Sewage And Sullage Water100% completed
|
|
Done |
Water Conservation, Rain water Harvesting50% completed
|
|
Work In Progress |
Water Supply100% completed
|
|
Done |
Buildings / Wings in Wing B Of Composite Building No 1 Imperial Edge
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Wing B Of Composite Building No 1 Imperial Edge by Sd Corporation Private Limitedlast updated on 14 Jan 2025
as per information obtained from MARA RERA.
Apartments Statistics
46
apartments in total
Saleable Area Statistics (Sq. ft.)
70875
Total
Total 46 apartments in project. 40 apartments booked. 86% apartments booked.
Total 70875 Sq.ft. saleable area. 61630 saleable area booked.
87% area booked.
Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
The Imperial Edge | Dec 2020 | 51 | 1 | 2 | 1 | 21 | 0 | 1 |
Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
3 BHK | 143.14 Sq.mts. ( 1541 Sq.ft. ) | 46 | |
46 total apartments / 40 apartments booked. 86% apartments booked. |
Work Description in Building The Imperial Edge | Completion |
Excavation | |
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
Stilt Floor | |
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
X number of Basement(s) and Plinth | |
X number of Podiums | |
X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Sd Corporation Private Limited
for Project
Wing B Of Composite Building No 1 Imperial Edge
last updated on
14 Jan 2025
as per information obtained from MARA RERA.