Mauli Omkar Project at Malad East by Mauli Sai Developers (P51800001198)
  • Rating: 4.9
  • (34)

Mauli Omkar - Malad East

Project Details, Configuration & Prices
1 BHK415 Sq.ft. Carpet ₹ 90 Lacs All In
2 BHK571 Sq.ft. Carpet ₹ 1.40 Cr All In
Project overview
Mauli Omkar Project at Malad East by Mauli Sai Developers (P51800001198) is a Ready Possession Project with 1/2 BHK apartments / Flats starting from ₹ 90 Lakh onwards

Mauli Omkar is a Residential Project by Mauli Shivam Constructions. It is a 20 storey tower, located at Malad East. Near Kurar Metro Station. 10 min to Malad Railway Station and 5 min to Western Express Highway. Close proximity to schools, hospitals, malls, markets. Connectivity to the upcoming infrastructure. Well connected to all the daily convenience. It offers 1 and 2 BHK Residences. Has all modern amenities and facilities. Fully furnished ready to move in flats.
Mauli Omkar QR Code
Mauli Omkar
MahaRERA - P51800001198

Raheja Residency

₹ 1.95 Crs. onwards
Malad East
2 BHK apartments
View Details

Center Plaza

₹ 69.72 Lacs. onwards
Malad East
Office BHK apartments
View Details
Malad East
Office BHK apartments
View Details

Alta Monte Tower B

₹ 2.6 Crs. onwards
Malad East
2/3/4 BHK apartments
View Details

Omkar Signet

₹ 95 Lacs. onwards
Malad East
1/2 BHK apartments
View Details

Highland 1978

₹ 1.11 Crs. onwards
Malad East
1/2 BHK apartments
View Details

Tower 28 - C and F

₹ 1.29 Crs. onwards
Malad East
2/3 BHK apartments
View Details

DGS Sheetal Shree Ramkunj

₹ 88.97 Lacs. onwards
Malad East
1/2/3 BHK apartments
View Details
Project Details
Project details were last updated in Dec 2024
  • Project:
    Mauli Omkar
  • Location:
  • Malad East, Triveni Nagar
  • Const. Stage:
    Ready Possession
  • Possession:
  • Parking:
    Open;
  • Floors:
    20
Developer Details

  • Developer:
    Mauli Sai Developers
  • Phone:
  • Website:
    www.maulisaidevelopers.com
  • Address:
  • Ground Floor, Mauli Pride, A-Wing, Kurar Village, Malad (E), Mumbai 400097
Project Ratings
Project Brochures
Brochures of Mauli Omkar by Mauli Sai Developers
Project Brochures
  • MPE/Brochures/9233/Mauli Omkar 1 Pdf.pdf
Project Amenities
Amenities offred in Mauli Omkar
LIFESTYLE AMENITIES
Kid's play areaSwimming PoolClub HouseGrand entrance lobbyHigh speed elevatorsPower BackupGymnasiumIndoor GamesPower BackupVitrified flooringPOP finished wallsIntercom/CCTVGranite PlatformModular Kitchen
Project RERA Details
RERA Project Status On-Going Project
Proposed Possession 08 Jul 2021
Revised Possession 08 Jul 2023
Extended Possession 07 Jul 2027
Litigations Yes
Project RERA Details
MAHA RERA No: P51800001198
RERA Project Name Mauli Omkar
RERA Location Vaishet Pada, Triveni Nagar, Triveni Nagar, Vaishet Pada, Mumbai Suburban, 400097
RERA Developer Mauli Sai Developers Pvt Ltd
Architect Mangesh Gosavi
Project RERA Details
Project Type Residential
Funding Bank HDFC BANK
Last Modified 24 Jan 2024
Last Retrived 16 Jan 2025

Most active Channel Partners, Real Estate Agents in Malad East

Facilities & Amenities
Facilities, Amenities & Common areas details of Mauli Omkar last updated on 16 Jan 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
1B &Amp; 2B Is Completed
Community Buildings
1B &Amp; 2B Is Completed
Electrical Meter Room, Sub-Station, Receiving Station75% completed
75% Complete
Wing 1A
Energy management
1B &Amp; 2B Is Completed
Fire Protection And Fire Safety Requirements70% completed
70% Complete
For Wing 2A
Landscaping & Tree Planting50% completed
50% Complete
For Wing 2A
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)80% completed
80% Complete
Wing 1A
Solid Waste Management And Disposal70% completed
70% Complete
Na
Storm Water Drains70% completed
70% Complete
1B &Amp; 2B Is Completed
Street Lighting60% completed
60% Complete
Wing 1A
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed
Water Conservation, Rain water Harvesting60% completed
60% Complete
Wing 1A
Water Supply80% completed
80% Complete
For Wing 2A
Buildings / Wings in Mauli Omkar
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mauli Omkar by Mauli Sai Developerslast updated on 16 Jan 2025 as per information obtained from MARA RERA. Disclaimer

65136 Sq. ft.

Project Area

9512 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

609 apartments in total
Total
609
Booked
385
Available
224

Saleable Area Statistics (Sq. ft.)

195744 Total
Total
195744
Booked
121836
Available
73907
Total 609 apartments in project. 385 apartments booked. 63% apartments booked.
Total 18185.03 saleable area. 11318.88 apartments booked.
62% area booked.

Omkar 1A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Omkar 1AAug 2021201010014
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
REHAB RESI24.99 Sq.mts. ( 269 Sq.ft. )228
228 Booked100% Booked
100% Booked
SALE COMMERCIAL S116.64 Sq.mts. ( 179 Sq.ft. )1
None Booked0% Booked
0% Booked
SALE COMMERCIAL S286.84 Sq.mts. ( 935 Sq.ft. )1
None Booked0% Booked
0% Booked
SALE COMMERCIAL S372.98 Sq.mts. ( 786 Sq.ft. )1
None Booked0% Booked
0% Booked
SALE COMMERCIAL S464.71 Sq.mts. ( 697 Sq.ft. )1
None Booked0% Booked
0% Booked
232 total apartments / 228 apartments booked. 98% apartments booked.
Work Description in Building Omkar 1ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Omkar 1B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Omkar 1BAug 202120101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.89 Sq.mts. ( 354 Sq.ft. )14
14 Booked100% Booked
100% Booked
1 BHK33.22 Sq.mts. ( 358 Sq.ft. )22
22 Booked100% Booked
100% Booked
1 BHK33.89 Sq.mts. ( 365 Sq.ft. )19
19 Booked100% Booked
100% Booked
1 BHK34.23 Sq.mts. ( 368 Sq.ft. )17
17 Booked100% Booked
100% Booked
72 total apartments / 72 apartments booked. 100% apartments booked.
Work Description in Building Omkar 1BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Omkar 2A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Omkar 2AJul 2024211010025
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
SALE RES 1 BHK27.91 Sq.mts. ( 300 Sq.ft. )147
None Booked0% Booked
0% Booked
SALE RES 1 BHK30.15 Sq.mts. ( 325 Sq.ft. )42
None Booked0% Booked
0% Booked
189 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Omkar 2ACompletion
Excavation
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Omkar 2B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Omkar 2BAug 2021211010025
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.95 Sq.mts. ( 290 Sq.ft. )19
18 Booked94% Booked
94% Booked
1 BHK35.32 Sq.mts. ( 380 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK36.43 Sq.mts. ( 392 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK36.62 Sq.mts. ( 394 Sq.ft. )40
35 Booked87% Booked
87% Booked
1 BHK38.57 Sq.mts. ( 415 Sq.ft. )35
18 Booked51% Booked
51% Booked
2 BHK53.07 Sq.mts. ( 571 Sq.ft. )20
14 Booked70% Booked
70% Booked
116 total apartments / 85 apartments booked. 73% apartments booked.
Work Description in Building Omkar 2BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Project Consultants
Channel Partners Registered by Developer
Mauli Sai Developers
for Project
Mauli Omkar
last updated on 16 Jan 2025 as per information obtained from MARA RERA. Disclaimer