Pallazio Project at Andheri East by Spenta Corporation (P51800002414)
  • Rating: 5.0
  • (104)

Pallazio - Andheri East

Spenta Corporation
Project Details, Configuration & Prices (Exclusive of Stamp Duty Charges, GST Charges, Registration Charges & Maintenance Charges)
1 BHK-796 Sq.ft.
₹1.27 Crore
1½ BHK-1030 Sq.ft.
₹1.64 Crore
2 BHK-1157 Sq.ft.
₹1.85 Crore
2 BHK-1240 Sq.ft.
₹1.98 Crore
Project overview
Pallazio Project at Andheri East by Spenta Corporation (P51800002414) a Sold Out Project with 1/1½/2 BHK apartments / Flats starting from ₹ 1.27 Crs onwards

Palazzio in Andheri is inviting, spacious and generous. These apartments offer a chance to live in a closely-knit community while still remaining in the heart of the Mumbai as it's well connected to almost anywhere.
Pallazio QR Code
Pallazio
MahaRERA - P51800002414

Rustomjee Central Park

₹ 81.46 Lacs. onwards
Andheri East
Office BHK apartments
View Details

Vasant Blossom

₹ 1.7 Crs. onwards
Andheri East
2/3 BHK apartments
View Details

Lodha Acenza

₹ 4.88 Crs. onwards
Andheri East
3/4 BHK apartments
View Details

Dynamix Luma

₹ 1.9 Crs. onwards
Andheri East
2/3 BHK apartments
View Details

Horizon Heights

₹ 1.33 Crs. onwards
Andheri East
1/2/3 BHK apartments
View Details

Horizon Tower 1

₹ 2.81 Crs. onwards
Andheri East
3 BHK apartments
View Details

Ganga CHS

₹ 1.08 Crs. onwards
Andheri East
1/2/3 BHK apartments
View Details

Sheth Vasant Oasis Jolan Tower 14

₹ 2.87 Crs. onwards
Andheri East
3 BHK apartments
View Details
Project Details
Project details were last updated in Dec 2024
  • Project:
    Pallazio
  • Location:
  • Andheri East, Aditya Textiles Compound, Andheri Kurla Road, Nr. Safed Pool
  • Const. Stage:
    Sold Out
  • Possession:
  • Floors:
    12
Developer Details

Spenta Corporation

  • Developer:
    Spenta Corporation
  • Phone:
    022 61295555
  • Website:
    www.spentacorporation.com
  • Address:
  • 3A/B, Rajabahadur Mansion, 20 Ambalal Doshi Marg, Fort, Mumbai - 400023.
Project Ratings
Project Amenities
Amenities offred in Pallazio
LIFESTYLE AMENITIES
Swimming PoolClub HouseHealth ClubGymnasiumGrand entrance lobbyHigh speed elevatorsJogging TrackLandscaped gardenKid's play areaPower BackupVitrified flooringPOP finished wallsIntercom/CCTVGranite Platform
Project RERA Details
RERA Project Status On-Going Project
Proposed Possession 31 Dec 2013
Revised Possession 31 Dec 2017
Extended Possession 31 Dec 2018
Litigations No Litigations
Project RERA Details
MAHA RERA No: P51800002414
RERA Project Name Palazzio
RERA Location Mumbai Suburban, 400072
RERA Developer Spenta Builders Private Limited
Project RERA Details
Project Type Residential
Funding Bank HDFC
Last Modified 30 Jun 2021
Last Retrived 15 Jan 2025
Facilities & Amenities
Facilities, Amenities & Common areas details of Pallaziolast updated on 15 Jan 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
No Receiving Station.
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Mcgm Approval
Landscaping & Tree Planting100% completed
95% Complete
As Per Mcgm Approval
Open Parking100% completed
95% Complete
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
As Per Mcgm Approval
Solid Waste Management And Disposal100% completed
95% Complete
As Per Mcgm Approval
Storm Water Drains100% completed
95% Complete
As Per Mcgm Approval
Street Lighting
Restricted To Driveways Within Property
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
As Per Mcgm Approval
Water Conservation, Rain water Harvesting95% completed
95% Complete
As Per Mcgm Approval
Water Supply
Will Receive After Occupation Certificate
Buildings / Wings in Pallazio
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Pallazioby Spenta Corporationlast updated on 15 Jan 2025 as per information obtained from MARA RERA. Disclaimer

69772 Sq. ft.

Project Area

13982 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

183 apartments in total
Total
183
Booked
181
Available
2

Saleable Area Statistics (Sq. ft.)

122765 Total
Total
122765
Booked
121411
Available
1354
Total 183 apartments in project. 181 apartments booked. 98% apartments booked.
Total 11405.11 saleable area. 11279.36 apartments booked.
99% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJan 19001212102251
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK70.96 Sq.mts. ( 764 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK55.23 Sq.mts. ( 594 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK69.1 Sq.mts. ( 744 Sq.ft. )4
4 Booked100% Booked
100% Booked
3 BHK70.82 Sq.mts. ( 762 Sq.ft. )7
6 Booked85% Booked
85% Booked
3 BHK73.52 Sq.mts. ( 791 Sq.ft. )7
7 Booked100% Booked
100% Booked
3 BHK90.7 Sq.mts. ( 976 Sq.ft. )4
4 Booked100% Booked
100% Booked
3 BHK93.69 Sq.mts. ( 1008 Sq.ft. )4
4 Booked100% Booked
100% Booked
43 total apartments / 42 apartments booked. 97% apartments booked.
Work Description in Building Wing ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJan 1900121210646
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK43.78 Sq.mts. ( 471 Sq.ft. )13
13 Booked100% Booked
100% Booked
1.5 BHK55.97 Sq.mts. ( 602 Sq.ft. )4
4 Booked100% Booked
100% Booked
1.5 BHK56.24 Sq.mts. ( 605 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK61.16 Sq.mts. ( 658 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK62.3 Sq.mts. ( 671 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK47.42 Sq.mts. ( 510 Sq.ft. )7
7 Booked100% Booked
100% Booked
2 BHK49.43 Sq.mts. ( 532 Sq.ft. )7
7 Booked100% Booked
100% Booked
43 total apartments / 43 apartments booked. 100% apartments booked.
Work Description in Building Wing BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CJan 19001212101438
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK54.7 Sq.mts. ( 589 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK54.93 Sq.mts. ( 591 Sq.ft. )13
12 Booked92% Booked
92% Booked
2 BHK69.08 Sq.mts. ( 744 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK71.59 Sq.mts. ( 771 Sq.ft. )8
8 Booked100% Booked
100% Booked
43 total apartments / 42 apartments booked. 97% apartments booked.
Work Description in Building Wing CCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DJan 1900121210475
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.35 Sq.mts. ( 402 Sq.ft. )6
6 Booked100% Booked
100% Booked
1 BHK48.86 Sq.mts. ( 526 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK59.31 Sq.mts. ( 638 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK61.12 Sq.mts. ( 658 Sq.ft. )8
8 Booked100% Booked
100% Booked
3 BHK77.66 Sq.mts. ( 836 Sq.ft. )14
14 Booked100% Booked
100% Booked
3 BHK94.73 Sq.mts. ( 1020 Sq.ft. )8
8 Booked100% Booked
100% Booked
54 total apartments / 54 apartments booked. 100% apartments booked.
Work Description in Building Wing DCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Project Consultants
Channel Partners Registered by Developer
Spenta Corporation
for Project
Palazzio
last updated on 15 Jan 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Spenta Corporation

Spenta Corporation Founded in 1989, Spenta is Mumbai's leading real-estate developer. Under the leadership of Aspan Cooper, Farshid Cooper and Anaisha Cooper, Spenta has created and delivered value with the design and development of every new real-estate project in Mumbai Over these past 25 years, Spenta has redefined the landscape of Mumbai, dotting its skyline with landmarks across Forjett Street, Hughes Road, Altamount Road, Walkeshwar, Breach Candy, Tardeo, Andheri, Powai, Chembur, Thane and Mahim that demonstrate its real-estate development prowess. Spenta is transforming over 12 million square feet of Mumbai into iconic residential towers, office spaces, housing complexes and shopping arcades, each a hallmark of intelligent space planning and keen attention to detail. Creating homes in Mumbai is what they as real-estate developers do best as Spenta is known for its ability to create a balance between inner and outdoor spaces, with efficient use of livable space without any compromise on quality that moves them up into the top real-estate league. Known to bring in on the same platform, the most respected names in the housing and real-estate sector, their homes in Mumbai today have become a testimony of their quality, design and craft. Today, Spenta's commitment to excellence in real-estate and innovation extends across the length and breadth of Mumbai with the redevelopment of certain handpicked projects - one of the many steps taken towards becoming the most reputed real-estate developers in Mumbai. Spenta's vision and mission statements also echo their desire, aspirations and what they work towards.